For purchasing uncompleted projects, or building under construction, payments will come progressively.
After completing the initial stage for booking the unit, exercising the Sales & Purchase Agreement (S&P) and Stamp Duty payments, progressive payment will begin depending on the stage of the construction.
Estimated Timeframe | Stage | Payment |
---|---|---|
Est. 6 – 12 months 大约6-12个月 |
Completion of Foundation Work 完成地基 |
10% |
Est. 6 – 9 months 大约6-9个月 |
Completion of Reinforces Concrete Framework of the unit 完成三合土框 |
10% |
Est. 3 – 6 months 大约3-6个月 |
Completion of brick walls of the unit 完成砖墙 |
5% |
Est. 3 – 6 months 大约3-6个月 |
Completion of roofing / ceilings of the unit 完成天花板和屋顶 |
5% |
Est. 3 – 6 months 大约3-6个月 |
Completion of electrical wiring, internal plastering, plumbing & installation of door & window frames of the unit 完成门,窗框,电线,水管及内部抹灰 |
5% |
Est. 3 – 6 months 大约3-6个月 |
Completion of carparks, roads, & drains serving the development 完成停车场,道路与沟渠 |
5% |
Est. 3 – 6 months 大约3-6个月 |
Notice of Vacant Possession (Temporary Occupation of Permit – TOP) 临时入伙纸发出 |
25% |
Est. 1 – 12 months 大约1-12个月 |
On Certification of Statutory Completion (CSC) 入伙纸发出 |
15% |
The estimated timeframe might vary between different projects.